Abilene Crane Permits and Rules: Streets, Airspace, Power Lines, Roads, Digging
Six sets of rules can stand between a crane and its first pick in Abilene, and each belongs to a different authority. The City of Abilene's Public Works Engineering Division permits work in a street or right-of-way. The FAA's notice rule, the City's airport zoning and the Air Force's land-use studies frame the height questions around Abilene Regional Airport and Dyess Air Force Base. OSHA, the Texas Health and Safety Code and AEP Texas's published contractor rules set how close a crane may work to a power line. The Texas Department of Motor Vehicles permits an oversize crane on the highway, Texas Utilities Code chapter 251 (the Texas 811 law) and OSHA's excavation rules govern digging, and OSHA's crane standard sets who may operate, rig and signal.
Each section below names the rule, the body that wrote it and, where the official page shows one, its date, so you can check the source yourself before a date is booked. The agencies make the final call; where we found no published rule, the section says so rather than guessing. The same checks go into every quote we write: the overhead-line distances and the FAA notice criteria are run against your site before a lift, and when a crane or machine has to stand on a City street, the quote names the permits, bond, licenses and traffic arrangements before a date is set. The heat, gust and project numbers that sit behind these rules are on our Abilene project and weather numbers page.
City of Abilene Rules for Cranes in Streets and Right-of-Way
Work in a City of Abilene street right-of-way starts with the Engineering Division of the Public Works Department. The City's Engineering FAQ says all work in the public right-of-way must be permitted through that division, and it names sidewalks, curb and gutter and driveways, new or repaired. Before the permit, the owner or contractor gives the City a Street Contractor's Bond of $1,000. The City's Inspection Services page adds that most insurance companies write the bond, that it must expire December 31 of the current year, that it is not the same as a Contractor's Bond, and that the Design Services office issues the permit once the bond is in. A crane set-up is not named on those pages, so before a mobile crane puts outriggers on a curb lane or a sidewalk, we ask the Engineering Division which permit covers it.
Inspection Services checks concrete forms in the right-of-way before any pour and books inspections by phone: call by 3 pm for an inspection the next morning, or by 10 am for one that afternoon. A form that passes gets a blue notice and one that fails a yellow notice; the first re-check after corrections is free, and later re-inspections for the same problem carry a fee. The City's Technical Specification Item 502 has traffic control devices follow the plans or the Texas Manual on Uniform Traffic Control Devices, wants a Registered Professional Engineer's seal on a contractor's traffic plan with major changes, and wants a competent person named in writing before work starts. At the federal level, OSHA sends construction signs and barricades (29 CFR 1926.200) and flaggers (29 CFR 1926.201) to Part 6 of the MUTCD.
The City fee schedule prices an Outside of Downtown Street Use License, for "any other private use upon any public street, alley, sidewalk or public way", at $100, and lists a $300 category for fireworks, pyrotechnics and events that the Special Events page describes as posing "a special hazard to the general public and property due to the nature of the equipment involved"; that page, whose applications Parks and Recreation coordinates, sets a 60-day application deadline for both. Both were written for events, and we found nothing on the City's site setting a permit, fee or lead time for a crane parked in a travel lane, so we work out the closure with Public Works Engineering before committing to a date. Job-site vehicles can park on the street past posted time limits with a Construction Parking Permit from Traffic and Transportation, $3 per vehicle per day, Monday through Friday.
- Street parking for trucks: under the City's Semi Parking Regulations (revised 2005), a commercial vehicle with a rated capacity above one ton stays off public streets, alleys, parkways and boulevards except in the Heavy Commercial, Light Industrial and Heavy Industrial districts, and even there it may not park on an expressway, arterial or collector street.
- Off-street storage: commercial vehicles of over one and one-half ton manufactured capacity, truck tractors, road tractors and special mobile equipment may be parked or stored only in the HC, LI and HI zoning districts.
- 18-wheelers: the City's Code Compliance FAQ answers no to parking them on a residential street, and reports go to the Abilene Police Department's non-emergency line.
- Sidewalks and curbs: the adjacent property owner is responsible for their repair and maintenance, the Engineering FAQ says, citing Chapter 29, Article III of the Municipal Code.
- Outside the city limits: Taylor County charges $25 for a permit to build a driveway on county road right-of-way, and the Air Force's AICUZ study notes that the county has no zoning authority.
Airspace Around Abilene Regional Airport and Dyess AFB
Abilene Regional Airport's FAA airport diagram for the October 2026 chart cycle shows a field elevation of 1,791 feet and two parallel runways, 17R-35L and 17L-35R, with sizes printed as "7198 X 150" and "7208 X 150" (length by width, in feet). The FAA's takeoff procedures for the field name the obstacle that shaped the Runway 17L departure route, a 2,758-foot MSL tower. ABI's runways run well past the 3,200-foot length that 14 CFR 77.9(b)(1) uses as its test, so the notice triggers in 14 CFR 77.9 put a 100-to-1 imaginary surface over the land for 20,000 feet outward from the closest point of the closest runway, and a temporary crane that would poke through it needs FAA notice. Away from airports, notice is still due for construction more than 200 feet above ground level at its site, or whenever the FAA asks.
The City of Abilene adds a height rule of its own through Planning and Development Services. Its brochure on the Airport Zone Development Permit, updated in 2010, requires that permit for any development, construction, repair, remodeling or change in use within the area the Airport Zoning Ordinance regulates, inside or outside the city limits, and bars any structure or obstruction above the heights on the Imaginary Surfaces Maps at the Planning Department, which are based on the runways' elevations. Structures 150 feet or more in height must obtain an FAA Determination of No Hazard. Near Dyess, structures under 50 feet tall in Accident Potential Zone I and under 150 feet in Zone II and beyond are exempt, and the permit has no separate fee. The brochure speaks of structures and obstructions, so before a tall lift we ask the department how it treats a temporary boom.
Dyess Air Force Base lies inside the Abilene city limits, next to the city of Tye. The Air Force's AICUZ study, using 2013 data, measures Runway 16/34 at 13,500 feet long by 300 feet wide, and each assault landing zone at 3,500 feet long by 60 feet wide. The October 2008 study sets the airfield elevation at 1,789 feet above mean sea level and the Outer Horizontal Surface at 2,289 feet MSL, and notes that rising land about 5 miles south and west of the field penetrates that surface. The City's Joint Land Use Study summary, revised in 2018, recommends a Red, Yellow, Green map showing where tall structures fit and recommends that Abilene and Tye require Part 77 obstruction evaluations for development that meets the FAA's notice criteria.
- File early: the FAA wants Form 7460-1 no later than 45 days ahead of the start (14 CFR 77.7), and its Part 77 page for airports suggests 45 to 60 days, given the time an aeronautical study takes; that page's list of temporary construction examples includes "Cranes, Boom Trucks".
- Form and fee: the 04/20 edition of Form 7460-1, filed online through the FAA's OE/AAA system, asks how long a temporary structure such as a crane will be up, lists no filing fee, and warns of a civil penalty of $1,000 per day for knowingly failing to file.
- Determinations: the FAA decides hazard or no hazard (14 CFR 77.31); a No Hazard finding may limit temporary construction equipment and recommend marking and lighting, and it lapses 18 months from its effective date unless the FAA extends, revises or terminates it, while "A Determination of Hazard to Air Navigation has no expiration date" (14 CFR 77.33).
- Emergencies: the 45-day lead time is waived when immediate work is required "because of an emergency involving essential public services, public health, or public safety", but the completed form still has to reach the FAA within 5 days of the first notice (14 CFR 77.7).
- Dyess safety zones (AICUZ studies of 2008 and 2015): clear zones 3,000 feet wide by 3,000 feet long, Accident Potential Zone I 3,000 feet wide by 5,000 feet long and Zone II 3,000 feet wide by 7,000 feet long, drawn for Runway 16/34.
- Air Force obstruction criteria follow FAA Part 77, Subpart C, and the AICUZ study advises anyone planning vertical structures near the base to start coordination with the FAA and Dyess early.
- Ahead of any lift near ABI, Dyess or another airfield, we run the site through 14 CFR 77.9 and the City's airport zoning, then tell you if a Form 7460-1 filing is needed and what the City asks for.
Power Lines: OSHA's 20 Feet, Texas's 6 Feet and AEP Texas Rules
For lines up to 350 kV, OSHA's power line rule, section 1926.1408, begins with a test: could the boom, the hoist rope, the load or its rigging come within 20 feet of a line anywhere in the work zone, which may be drawn as 360 degrees around the machine out to its maximum working radius? If yes, there are three routes: the utility confirms the line "has been deenergized and visibly grounded at the worksite", the crew holds everything 20 feet off, or the employer gets the voltage from the utility, which must answer within two working days, and keeps to the Table A distance below. Every line is treated as live until the utility says otherwise, and the rule adds a crew planning meeting, any tag lines made non-conductive, a warning line, barricade or row of signs the operator can see, and one or more of the listed safeguards.
Texas draws a line at six feet. Health and Safety Code section 752.004 forbids any activity in which a person, or any part of a tool, machine, equipment or material, could come within six feet of a high-voltage overhead line (over 600 volts), unless the danger is guarded against under section 752.003. Health and Safety Code section 752.003 starts a 48-hour clock for whoever runs the temporary work: the line's operator gets notice at least 48 hours ahead, and nothing begins until the two sides have a deal: the line de-energized and grounded, relocated or raised for the job, or separated from the work by mechanical barriers. The party doing the work pays the operator's actual cost, in advance if asked, and gets any surplus back. Under section 752.007 a violation is a crime: a fine from $100 up to $1,000, jail of up to one year, or both.
The DCOA names AEP Texas as Abilene's incumbent electric utility, the company that owns and keeps up the local lines, and the Public Utility Commission of Texas's 2019 market report calls AEP Texas a TDU operating in ERCOT. AEP Texas's contractor safety page sets a 10-foot buffer between anything energized and both crews and their equipment, and it tells crane users to learn the minimum distance their crane can work near a line and to keep crane and load outside it unless the line is de-energized and grounded. Its other crane rules: one worker assigned to signal the operator, nobody touching a crane that is working near a line, slower hoisting, booming, swinging and travel, and tag lines of dry polypropylene. It also warns against relying on proximity warning devices, hook insulators, insulating boom guards or cages, or swing limit stops.
- Table A in 29 CFR 1926.1408, voltage then distance: to 50 kV, 10 feet; past 50 and up to 200 kV, 15 feet; past 200 and up to 350 kV, 20 feet; past 350 and up to 500 kV, 25 feet; past 500 and up to 750 kV, 35 feet; past 750 and up to 1,000 kV, 45 feet; above 1,000 kV, the distance is "as established by the utility owner/operator or registered professional engineer who is a qualified person".
- OSHA's listed safeguards, at least one required: a proximity alarm, a dedicated spotter in continuous contact with the operator, a device that warns the operator to stop, a device that limits range of movement, or an insulating link.
- Over 350 kV, 29 CFR 1926.1409 puts 50 feet in place of 20 feet for lines up to 1,000 kV.
- Moving with no load: Table T in 29 CFR 1926.1411 sets travel clearances from 4 feet at 0.75 kV or less up to 20 feet in the band over 750 to 1,000 kV, and a dedicated spotter is required if any part of the machine will come within 20 feet.
- Assembly or teardown below a power line is off limits until the utility has deenergized it and visibly grounded it at the worksite (29 CFR 1926.1407).
- AEP Texas notes that clearance distances grow as the span between poles or towers grows; if a crane touches a line, its Look Up for Lines sheet says to stay in the cab and call 911 and the power company.
- Man lifts: OSHA's aerial lift fact sheet treats every overhead power line and communication cable as live and keeps workers and their lift 10 feet or more away; our boom lift rental page covers the lift side.
- Transmission: AEP Texas's Abilene South-Putnam project is about 33 miles of 138-kV line on single-pole steel structures, typically 76 feet tall on a 100-foot right-of-way (fact sheet dated 09/12/2024).
- Our pre-lift check holds the site up against OSHA's distances and the Texas 6-foot law with its 48-hour notice, and we spell out which arrangements are needed and whose job each one is.
TxDMV Permits, Escorts and Abilene Truck Routes for Cranes
No permit is needed while a load stays inside TxDMV's legal box: width 8 feet 6 inches, height 14 feet, 45 feet for a single motor vehicle, 59 feet for a semitrailer in a two-vehicle combination, and 80,000 pounds gross. Axle caps: single 20,000, tandem 34,000, triple 42,000 and quad 50,000 pounds. Outside the box, an oversize/overweight permit is required, applied for with the exact dimensions and weight in hand. TxDMV's General Single-Trip permit, valid for a single move of a load to 254,300 pounds, costs $60, and a load above 80,000 pounds adds a highway maintenance fee that climbs through four weight bands from $150 to $375; past 200,000 pounds, TxDMV adds a $35 vehicle supervision fee and wants 95 feet or more of total axle spacing. Beyond that sits the Superheavy permit, which TxDMV says to seek "three to four weeks before the permit is needed".
A self-propelled crane has its own permits. The annual permit for unladen lift equipment (TxDMV's Unladen Lift Equipment page), whose $100 fee is set in Transportation Code section 623.182, stretches the limits to a 10-foot width at legal height and length and a 120,000-pound gross, with caps of 25,000 pounds on a single axle, 46,000 pounds on a tandem group and "650 pounds per inch of tire width", and it lapses one year after its movement-to-begin date. Cranes on it may travel at any hour at no more than 9' wide, 14' high and 65' long, and after dark with an escort at each end if they measure no more than 95 feet long and 14 feet high and no wider than 10 feet 6 inches. The single-trip mileage version runs up to seven consecutive days from a $31 minimum, with no single axle above 30,000 pounds.
Trucks in Abilene follow a practice, not an ordinance. The Abilene MPO's 2050 Metropolitan Transportation Plan, approved December 17, 2024, describes a controlled-access loop, with IH 20 across the north, SL 322 around the east and southeast and US 83 down the west and southwest, that helps keep truck through-traffic off the arterials "in lieu of a City of Abilene truck route ordinance", and it flags "turning radii at major intersections, vertical clearance at grade separations" as the limits on truck moves. A heavy haul also has to work around the I-20 projects: TDLR's state registry dates TxDOT's IH 20 rebuild between FM 600 and SH 351 from 11/3/2026 to 10/16/2029, and TxDOT's proposed six-lane widening from west of the city limits runs 5.32 miles and reconfigures the US 277/US 83 interchange.
- Width escorts: a load past 14 feet wide takes one escort, ahead of it on a two-lane highway or behind it on a multi-lane one, and past 16 feet it takes two, front and rear, on every road.
- Escorts by height and overhang: TxDMV wants one front escort with a height pole for loads "Exceeding 17'" high and front and rear escorts "Exceeding 18'"; a front or rear overhang over 20 feet takes a rear escort, and a load over the limits in two dimensions takes escorts front and rear.
- Marking: a load that overhangs either side, or the rear by more than four feet, carries 12-inch red flags at its outermost points, and when the rear overhang passes the bed by more than four feet, two red lamps that can be seen from 500 feet behind go on its end.
- Daylight: 43 TAC section 219.11 keeps most permitted loads to daytime, a window that Transportation Code section 541.401 opens a half hour ahead of sunrise and closes a half hour past sunset; overweight-only loads, and interstate runs of 10 feet wide or less and 100 feet long or less with legal overhang, are exceptions.
- Holidays: on each holiday TxDMV lists, a load past any of three marks (14 feet wide, 16 feet high, 110 feet long) stays parked unless TxDMV grants an exception; still ahead this season are 11/26/2026 (Thanksgiving), 12/25/2026 (Christmas) and 01/01/2027 (New Year's Day).
- Curfews: the only Taylor County line on TxDMV's Time Permit Curfews list, in effect from September 30, 2025, is SH 153 from US 277 to SH 70, shared with Nolan County, where all oversize and overweight traffic is barred from 8 a.m. to 8 p.m. on Sundays; Abilene itself has no entry.
- Paperwork: most permits can be self-issued in TxPROS, TxDMV's online system, and a Superheavy route approval holds for 30 days from the movement date; our Abilene crane cost page lists the TxDMV fees beside the other public fees.
- Interchange work: TxDOT's new US 83/277 overpass at FM 3034, 0.9 miles in Taylor and Jones counties, began in October 2024 and is estimated for completion in spring 2027.
Digging: Texas 811, OSHA Trench Rules and Abilene's Clays
Texas sets the digging rule in the Utilities Code, chapter 251, whose definition of excavating covers mechanized equipment of any kind moving soil "to a depth of 16 or more inches", so an excavator, a backhoe or a powered auger all count. Section 251.151 opens the notice window on the 14th day before the dig and closes it at the 48th hour before, with Saturdays, Sundays and legal holidays left out of the count. Texas 811 puts the same duty as two business days, says the marking costs you nothing, and wants a fresh notice if work starts more than fourteen days after the first one. Section 251.157 gives Class A operators 48 hours to mark, in American Public Works Association colors, and Texas811's FAQ counts 18 inches on each side of a mark as the tolerance zone.
OSHA's Subpart P governs the open trench. Before the cut, 29 CFR 1926.651 has the employer estimate where the sewer, telephone, fuel, electric and water lines run, then pin down the exact spot as digging nears it; spoil and machines stay 2 feet or more from the edge or behind retaining devices; trenches 4 feet deep or more need a ladder, stairway or ramp "so as to require no more than 25 feet (7.62 m) of lateral travel for employees"; and a competent person inspects daily and after each rainstorm. Under 29 CFR 1926.652, the only cuts that skip cave-in protection are those made entirely in stable rock and those "less than 5 feet (1.52m) in depth" where a competent person's check finds no sign of a cave-in. Without another option, slopes may be no steeper than "one and one-half horizontal to one vertical (34 degrees measured from the horizontal)".
Abilene's soils give that after-rain inspection real weight. The Handbook of Texas describes Taylor County's loamy surface soils as reddish to brownish over clayey subsoils that often hold lime accumulations. The USDA's Abilene series, established in Taylor County in 1915, is very deep and moderately slowly permeable, with secondary carbonates starting "25 to 71 cm (10 to 28 in)" down, and its associated Hollister series is a shrink-swell clay whose cracks run "more than 76 cm (30 in) deep" and "remain open for 150 or more cumulative days during most years". For cuts under 20 feet, OSHA's Appendix B slopes run Type A soil 3/4:1, Type B 1:1 and Type C 1-1/2:1, and anything deeper needs a registered professional engineer's design. A trench dug with an excavator rental here starts with the 811 ticket.
- Hit a line? Report it to the line's operator at once and leave the area unfilled until the operator has the report and the two of you agree on a repair schedule (section 251.159); for a gas line, Texas811 says to call 911 as well.
- Penalties (section 251.201): a violation of section 251.151 or 251.159 can cost $500 to $1,000; a second inside a year, $1,000 to $2,000; a third inside a year, $2,000 to $5,000. A homeowner digging on the owner's own residential lot is outside that section.
- Exemptions in section 251.156 include agricultural operations on private property and routine maintenance by a county employee on a county road right-of-way to a depth of not more than 24 inches.
- Street and alley cuts: the City's Streets section bills repairs at actual material and labor cost, and its fee schedule lists four plumber's-ditch charges, each for a ditch of up to 12 cubic yards, from $451.56 to $1,633.77.
- City specifications: the City of Abilene's Technical Specifications include Item 402, Trench Excavation Protection, and Item 403, Temporary Special Shoring.
- On our jobs, whoever digs, us or you, makes the 811 call two business days ahead, as the statute sets out.
Who May Run, Rig and Signal a Crane: OSHA, NCCCO and Lift Plans
The operator rule, OSHA section 1926.1427, is written as an employer's duty to see each operator "trained, certified/licensed, and evaluated", and until then a person may run the crane only as an operator-in-training under supervision. A state or local license comes first wherever such a license is issued. Where none is, the operator is certified, either by an accredited testing organization for crane operators, whose certificate OSHA's 2018 rule calls portable and which lasts 5 years, or by an audited employer program, which also lasts 5 years but stays with that employer. The certificate does not finish the job. Each employer must still evaluate the operator on the skills its equipment calls for, including its size and configuration, and document the evaluation, a requirement in force since February 7, 2019. Equipment rated 2,000 pounds or less falls under the training rule of 29 CFR 1926.1441 instead.
NCCCO, a nonprofit founded in 1995, is one accredited certifying body; its program carries ANSI National Accreditation Board accreditation to ISO 17024, a certification lasts five years, and its accredited programs include mobile crane operator, Signalperson, Rigger Level I and Level II and Lift Director. Rental cranes get their own answers in OSHA's Cranes FAQ: a lessor that sends operators with its cranes has duties under the standard, its employee who assembles, hoists or travels on the site must meet the standard, and one who only moves the crane on or off the trailer is delivering, not doing construction. So on an operated rental from us, the operator we send falls under section 1926.1427 like any crane operator in construction, and on a bare rental the rule falls on your operator, which is why we ask who that will be before the quote is final.
A signal person is required under 29 CFR 1926.1419 when the operator cannot fully see the point of operation, when the view in the direction of travel is blocked, or when the operator or the person handling the load calls for one over site conditions. Before the first signal, 29 CFR 1926.1428 has that person's employer confirm the qualification, through documentation from a third-party qualified evaluator or through the employer's own qualified evaluator, whose finding is not portable, after "an oral or written test" and "a practical test". With workers in the fall zone, the load must be rigged by a qualified rigger (29 CFR 1926.1425), a rigger who meets OSHA's test for a qualified person. ASME's P30.1-2024 splits planning into "Standard Lift Plan and Critical Lift Plan"; our lift planning page walks through what each holds.
- Voice signals carry function, direction, distance and/or speed, then function stop, in that order (29 CFR 1926.1421); hand signals use the Standard Method chart, and only one person signals at a time (section 1926.1419).
- Radios: signal radios are tested on site before work, kept on a channel used only for signals, and heard by the operator hands-free (29 CFR 1926.1420).
- A dedicated spotter for power lines must meet the signal person qualifications of section 1926.1428, OSHA's definitions say.
- Assembly and disassembly are directed by an A/D director who is both a competent and a qualified person, or a competent person assisted by qualified persons (section 1926.1404).
- Authority to stop: the operator may stop and refuse to handle loads "whenever there is a concern as to safety", until a qualified person has determined that safety has been assured (29 CFR 1926.1418).
- Military option: OSHA's Cranes FAQ says the U.S. military qualification is only available to civilian and uniformed employees of the Department of Defense, so private contractors use one of the other options.
- We ask that anyone running a forklift, telehandler or aerial lift from us be trained as OSHA (29 CFR 1910.178 and 1926.602) and ANSI/SAIA A92.22 and A92.24 require.
Send us the address, the load and the dates, and the free written quote lists each permit, notice and line clearance the job needs.
Quick Answers
Is a City permit required to set up a crane on an Abilene street?
Plan on City paperwork before the crane arrives. The City of Abilene's Engineering FAQ routes every job in the public right-of-way through the Engineering Division of Public Works, and a $1,000 Street Contractor's Bond has to be on file before that permit issues. The City's street use licenses, $100 for private use of a public way outside downtown and $300 for the fireworks, pyrotechnics and hazardous-equipment category, take applications 60 days ahead and are aimed at events. No City page we read covers a crane in a travel lane, so the permit and any lane closure are confirmed with the Engineering Division before we book the date.
How far must a crane stay from power lines in Abilene?
Plan on 20 feet from any line up to 350 kV under OSHA section 1926.1408, unless the utility deenergizes and grounds it or gives the voltage so a Table A distance applies; that table starts at 10 feet for 50 kV and below and grows with voltage. Texas law sets a separate six-foot floor for lines above 600 volts: nothing comes that close until the line's operator has notice at least 48 hours ahead and the two sides agree to de-energize, move or guard the line. AEP Texas, the local wires utility, asks contractors to keep 10 feet from anything energized.
When do I need to file FAA Form 7460-1 for a crane in Abilene?
File under 14 CFR 77.9 if the crane will reach more than 200 feet AGL (above ground level) at its site, if it will rise through one of the FAA's imaginary surfaces, or if the FAA asks. Abilene Regional Airport's runways exceed the 3,200-foot test, so a 100-to-1 surface stretches 20,000 feet out from the nearest runway, and even a modest boom near the field can cross it. The FAA needs the form 45 days or more before the work and suggests 45 to 60 days. Separately, the City's airport zoning wants an FAA Determination of No Hazard for any structure of 150 feet or more.
Does a crane need a permit to drive on Texas highways?
Only when it breaks a TxDMV legal limit, such as 80,000 pounds gross, 20,000 pounds on a single axle, a width of 8 feet 6 inches or a height of 14 feet. A self-propelled crane over legal width or weight can run under TxDMV's yearly permit for unladen lift equipment, which costs $100 and reaches 10 feet of width and 120,000 pounds gross, or on a mileage permit for one trip, which starts at $31 and lasts up to seven consecutive days. A crane or machine hauled over legal size on a trailer moves on a General Single-Trip permit, which costs $60 before the highway maintenance fee charged above 80,000 pounds, or on a Superheavy permit.
Who calls 811 before digging in Abilene, and how far ahead?
The excavator does, and Texas law sets the timing. Any mechanized digging that moves soil "to a depth of 16 or more inches" needs a locate request, and Texas811's FAQ says yes even to people who are not digging very deep. Texas Utilities Code section 251.151 sets a window from the 14th day to the 48th hour before work, not counting weekends and legal holidays, which Texas811 puts as two business days. Marking costs you nothing, Class A operators mark within 48 hours, and a new notice is needed if the start slips beyond fourteen days. On our jobs, we or you make that call.
Does a crane operator need to be certified in Texas?
Yes for construction work, under federal OSHA's crane standard: section 1926.1427 makes the employer see that each crane operator is "trained, certified/licensed, and evaluated", with narrow exceptions such as equipment rated 2,000 pounds or less. The certificate can come from an accredited testing organization (portable, and good for 5 years) or, without portability, from an audited employer program; NCCCO is one accredited certifying body. Holding a certificate does not end the employer's duty to evaluate the operator on the actual equipment. When you rent bare, the rule applies to your operator, and we ask who that is.