Abilene Crane Rental Co. Call (325) 308-1613
A dark blue truck crane on the shoulder of a two-lane highway lowers a precast concrete box culvert section on chain slings into a fresh ditch.

Abilene Crane Rental Co.

(325) 308-1613

Free quotes for mobile crane rental in Abilene, TX.

Mobile Crane Rental in Abilene, TX

For most single lifts in Abilene, the mobile crane that fits is a hydraulic truck crane, a telescopic boom built onto its own road-going carrier, and four local facts choose the model: the load chart at your radius, the soil under the outriggers, the AEP Texas wires near the pick, and the wind. A load chart is the maker's grid of rated loads by boom length and radius. Manitowoc defines radius as the "horizontal distance from axis of rotation to center of gravity of the freely suspended load", and outriggers are the beams and jacks that swing out and lift the carrier off its tires. Billed hourly against a minimum, the class pays off on one pick, the trade's word for a single lift, or on a short string of them.

Published price

$300 to $700 an hour for a mobile crane, national average (a national rental marketplace's cost guide, April 27, 2026) · full pricing guide

Think of the class as a crane and its own truck in one machine, with boom, counterweight and outriggers riding on a multi-axle carrier; it earns its place on lifts a boom truck cannot hold or reach that still wrap up within a shift, such as rooftop units, trusses, beams and tanks. Link-Belt's HTC-8675 Series II specifications rate it "75 USt @ 9 ft", with a 41 ft to 127 ft four-section boom and a 230 ft maximum tip height, and Link-Belt says it "Transports under 95,000 lbs with 14,400 lbs of counterweight, fly, and 10-t ball installed". Grove credits its TMS800-2 with 80 USt and a 65 mph top travel speed. On unimproved ground, weigh a rough-terrain crane instead; Tadano's GR-800XL-4 datasheet lists a 22 mph travel speed.

Every crane rate we found is national, and each climbs with tonnage. A crane cost guide posted April 27, 2026 by a nationwide equipment-rental marketplace puts the mobile crane average at "$300 to $700 per hour". Its mid-sized mobile row reads "$250 to $600/hour" bare, the crane alone, against "$400 to $750/hour" operated, with the operator on the bill; its 50-ton line reads "$150 to $300 per hour" and its 100-ton line "$250 to $600 per hour". Its operator line adds "$50 to $150 per hour to the standard rental costs", day minimums run three to eight hours, and short jobs can still be billed to the minimum or portal to portal. None is an Abilene rate; the cost page lines them up, and the tax rule is in the options below.

Four rule sets govern a truck crane lift here. OSHA's section 1926.1427 puts the duty on the employer: every operator has to be "trained, certified/licensed, and evaluated". OSHA's power line clearance rule, section 1926.1408, written for lines of up to 350 kV, starts with one test: can any part of the machine, the hoist rope or the load "(including rigging and lifting accessories)" come within 20 feet of the line? The Texas Health and Safety Code, in chapter 752, adds a six-foot boundary that no tool, machine or material may cross until the line's operator has been told "at least 48 hours before the work begins" and a clearance is agreed. On a City of Abilene street, the Engineering Division of Public Works permits the job, and the permit needs a $1,000 Street Contractors Bond.

Soil, heat and wind keep the schedule on an Abilene lift. The USDA NRCS series named Abilene, established in Taylor County in 1915, is a very deep soil formed in calcareous alluvium with lime 25 to 71 cm down, and Hollister clay, one of its listed neighbors, opens cracks "more than 76 cm (30 in) deep". Floats therefore go on mats or cribbing, and OSHA defines blocking, which it also calls cribbing, as "wood or other material used to support equipment or a component and distribute loads to the ground." NOAA's 1991-2020 normals give the airport 18.5 days a year of 100-degree highs, and NWS San Angelo counted 30 at Abilene in August 2026 alone. Wind sets the harder limit, with NOAA recording a 74.0 mph 5-second gust at the airport on June 21, 2023. Before the crane rolls, mark the set-up spot, anything buried under it and the way in.

Pricing starts with a few facts from you: the load's weight and size, the spot it sits now and the spot it must land (together they fix radius and lift height), the soil and the gate, any wires overhead, and the site address with your dates. The quote costs you nothing, comes in writing before anything moves, and breaks out each charge: which crane and what size, operated or bare, the hourly minimum, the drive in, permits, escort cars, mats, rigging and any tax. When the outriggers must land on a City street, sidewalk or right-of-way, we spell out the permits, bond, licenses and traffic control before a date goes on the calendar.

Free quote

Fields marked * are required.

Your quote comes in writing at no charge, and no crane or machine is scheduled until you say yes.

Published Figures for Five Example Truck Cranes

Five hydraulic truck cranes, side by side, as their builders rate them. Use the columns to narrow the class by capacity, boom, tip height and road weight; the final choice still comes from the load chart at your radius. Tadano sells the GT-750EL-3 for export and publishes it in metric only, so its cells stay metric.

Example model Max capacity Main boom Max tip height Transport weight Top travel speed
Link-Belt HTC-8675 Series II 75 USt @ 9 ft 41 ft - 127 ft, four sections 230 ft Under 95,000 lbs as transported not listed
Link-Belt HTC-86100 100 USt @ 7 ft 38 ft - 140 ft 237 ft Under 97,000 lbs as transported not listed
Link-Belt 120|HT 120 USt @ 7 ft 38.3 ft - 164.1 ft 262 ft 110,000 lbs as transported not listed
Grove TMS800-2 80 USt 39.4 ft - 128.0 ft 194.3 ft with lattice extension 74,448 lbs total gross vehicle weight 65 mph
Tadano GT-750EL-3 (export model, metric) 75 t 12.0 m - 47.0 m not listed not listed 85 km/h

Numbers come straight from each manufacturer's spec page or datasheet and are top-end ratings for that model. What a crane can hold on your job depends on its load chart for the boom, radius and counterweight in use. We chose these models to illustrate the class; none of them is a machine we own.

When a Truck Crane Fits an Abilene Lift

A truck crane is the call when the load has outgrown a boom truck or a telehandler, the hook time runs in hours, and the carrier can drive to firm ground. Each condition below points that way and brings a check we run before quoting.

  • Counting hook block and slings, the load at the set radius is beyond what a boom truck's chart allows.
  • The only workable set-up spot is a City of Abilene street or alley, so a permit and bond come first.
  • An AEP Texas line is within reach of the boom, hoist rope or load, so both OSHA's 20-foot test and the Texas six-foot law apply.
  • The ground there is clay still soft from the last rain, or it hides a tank, a vault or a buried line.
  • The job sits close enough to Abilene Regional Airport or Dyess that a tall boom could need FAA notice first.

Reading a Truck Crane Load Chart Before an Abilene Pick

The tonnage painted on a truck crane is what it lifts at its tightest radius, so the number that settles your job sits further down the chart, at your radius. Manitowoc says maximum capacity "is obtained at minimum radius with basic minimum boom length of a crane", which is why Link-Belt pins its HTC-8675 Series II rating to a 9 ft radius, and SANY puts the trade-off plainly: "the larger the lifting radius, the lower the maximum lifting capacity." Manitowoc's chart notes then take weight off the top, since hook blocks and rigging count against the rating: "Their total weight must be subtracted from the rated load to obtain the weight that can be lifted." Those notes also lower the rating for soft or uneven ground, an out-of-level setup, wind and side loads. OSHA's section 1926.1417 keeps the charts in the cab, forbids lifting past rated capacity, and wants the weight "determined from a source recognized by the industry (such as the load's manufacturer)" or an accepted calculation.

With neither, the operator starts the hoist and reads the load on the crane's indicator or limiter; past 75 percent of rated capacity at the farthest radius planned, the pick waits for a verified weight. Section 1926.1404 requires outriggers "either fully extended or, if manufacturer procedures permit, deployed as specified in the load chart", with the crane's weight off its wheels.

Power Lines on an Abilene Truck Crane Job: OSHA, Texas, AEP

Wires, more than iron, decide where a truck crane can stand in Abilene, where the DCOA says AEP Texas owns and maintains the local lines, and three rule books overlap. OSHA's section 1926.1408 has the employer mark out a work zone, which may be "the area 360 degrees around the equipment, up to the equipment's maximum working radius", then test whether crane, rope or load could get within 20 feet of a line. If so, there are three ways through: the utility de-energizes and grounds the line, everything holds 20 feet off, or the employer asks the utility for the voltage, answered inside two working days, and works to the Table A distance. AEP Texas's Abilene South-Putnam project, a 138-kV line, would carry a 15-foot Table A clearance.

In the zone, OSHA also wants a planning meeting, any tag lines (the hand ropes that steady a load) non-conductive, and one or more listed safeguards, from a proximity alarm or a dedicated spotter to a range limiter or an insulating link. Texas law keeps its six-foot floor, wants 48 hours' warning to the line's operator, bills the clearance to whoever does the work, and makes a breach a crime with fines from $100 up to $1,000 and up to a year in jail. AEP Texas's contractor safety page adds a 10-foot rule of its own and favors dry polypropylene for tag lines.

Street Set-Ups in Abilene and the Road Rules for Truck Cranes

Setting outriggers on a City of Abilene street takes paperwork before steel touches pavement. The Engineering FAQ is direct: "All work in the Public Right-of-Way (ROW) must be permitted through the Engineering Division" of Public Works, with a $1,000 Street Contractors Bond posted first. Inspection Services adds that the bond "must expire December 31 of the current year", and that Design Services issues the permit after the bond arrives. The fee schedule charges $100 for an Outside of Downtown Street Use License covering other private use of a public way, the Special Events page asks for that application 60 days ahead, and construction parking permits run $3 per vehicle per day, Monday through Friday.

No City page we found sets a rule written for a crane in a traffic lane, so we settle any closure with Public Works Engineering before booking. Over-limit highway moves can use TxDMV's annual permit for unladen lift equipment: $100 a year, with a 120,000-pound gross weight and 10-foot width limit. Neighboring towns differ. Merkel's truck rules cover "Any and all vehicles having three (3) or more axles and rated to be in excess of 12,000 pounds gross weight", keeping them to state routes unless delivering, and Anson's parking code bars trucks over 25 feet long or 8 feet wide from parking on streets that are not state roadways, except while loading or unloading with a driver.

Truck Crane Choices: Operated or Bare, Step Up or Down

Two questions shape almost every truck crane quote we write in Abilene: whose operator sits in the cab, and whether this class is the right tool at all. Each option gives the rule or figure behind it and the job it fits.

Operated truck crane rental

Operated means a person at the controls comes with the crane, billed hourly against a minimum, and OSHA section 1926.1427 holds that person to the "trained, certified/licensed, and evaluated" standard. Texas's Rule 3.294 says one charge covering equipment plus operator "shall be presumed to be the performance of a service and no tax may be charged", unless other parts of the Tax Code make the service taxable. It fits a crew with one lift and nobody to run a crane.

Bare truck crane rental

Bare means the crane comes alone and your own operator takes the seat, someone who meets the same section 1926.1427 test; we ask for that name before the quote is final. Here Rule 3.294 is blunt: "Receipts from the lease of tangible personal property without an operator are taxable," damage waiver and delivery charges included, with the Comptroller's combined rate for the City of Abilene at 8.25 percent. It fits a contractor that already employs a qualified operator.

Step up to an all-terrain

If your radius outruns every truck crane chart in the table, move up a class to an all-terrain crane; Tadano rates its AC 5.250-2 at 300 USt with a 378.2 ft maximum tip height. Expect more counterweight, a wider outrigger footprint and, on the biggest models, TxDMV trip permits and escort cars. It fits heavy mechanical sets and tall steel.

Step down to a boom truck

If the load is light and lands near the truck, a boom truck can do the work from one chassis. OSHA's crane standard counts it in, naming "boom truck cranes" among the mobile cranes in its scope, so this page's operator and power line rules still govern. It fits trusses, signs, light poles and ranch equipment.

Questions

Mobile Crane Rental FAQs

How much is a truck crane per hour in Abilene?

Nobody publishes an Abilene-only crane rate that we can cite, so national guides set the range. One nationwide equipment-rental marketplace's guide, dated April 27, 2026, lists small cranes at "$200 to $500 per hour" and large cranes at "$500 to $1,500 per hour". HomeGuide's tree-moving guide, written December 22, 2025, says "Crane rentals with operators cost $350 to $1,500 minimum for 4 to 6 hours." Your written quote costs nothing and lists every charge and any tax line.

Does a rented crane need a certified operator?

Yes. OSHA's section 1926.1427 requires the employer to ensure each operator is "trained, certified/licensed, and evaluated", and certification can come from a testing body with national accreditation or an audited employer program. When the crane comes operated, the person at its controls has to meet that section; on a bare rental your company supplies that person, and we ask who it is before the quote is final. NCCCO is one accredited certifying body, with a five-year certification period.

Can a truck crane lift near AEP Texas power lines?

Yes, after the clearances are settled. OSHA's section 1926.1408 asks whether machine, rope or load could swing or drift to less than 20 feet from a line carrying up to 350 kV; when the answer is yes, the line gets de-energized and grounded, the crew keeps 20 feet away, or the Table A figure for the line's voltage takes over. Texas chapter 752 adds its six-foot floor and the 48-hour notice. We check your site against both before the lift and say who arranges what.

Does a crane on an Abilene street need a City permit?

Yes. In the City's words, "All work in the Public Right-of-Way (ROW) must be permitted through the Engineering Division," and that permit needs a $1,000 Street Contractors Bond. A street use license, construction parking permits and traffic control may apply too. Our permit and airspace guide collects the City's rules, and we tell you which ones your set-up triggers before a date is chosen.

How big a crane does a rooftop HVAC unit need?

The answer comes from the unit's weight plus rigging, read against the chart at the radius from the crane's swing axis to the roof curb. Take the weight from the manufacturer's sheet, measure from the nearest firm parking spot to the curb, and note the roof height. Link-Belt's 75 USt rating for the HTC-8675 Series II holds only at 9 ft, so a curb far from the street can need a bigger crane than the weight suggests. Send us those three numbers.

Free Mobile Crane Rental Quote — Abilene

Free quote

Fields marked * are required.

Your quote comes in writing at no charge, and no crane or machine is scheduled until you say yes.